Short answer
The three do different jobs. Mediation is a negotiation led by a neutral who decides nothing. Arbitration ends in a binding award, and in Georgia the Arbitration Code is the exclusive means of enforcing an arbitration clause in a construction contract. A special master is appointed by a judge under Uniform Superior Court Rule 46 to handle defined tasks in a pending lawsuit. Your contract usually sets the order.
Three Tools With Three Different Starting Points
Owners, contractors, subcontractors and suppliers have three neutral-led tools for a construction dispute, and each begins in a different place.
- Mediation starts with agreement: a clause in the contract, a decision by the parties once a dispute arises, or a court referral in a filed case. The mediator helps the parties negotiate and decides nothing.
- Arbitration starts with a written agreement to arbitrate, usually a clause in the construction contract. The arbitrator hears evidence and issues an award.
- A special master exists only inside a lawsuit. A judge appoints the master to handle defined tasks in a pending case and reviews the master’s work.
So the first step is to read the contract and check whether a lawsuit is already on file. This guide uses Georgia law as the worked example, because GCAAM is based in Georgia; projects in other states follow their own statutes and court rules.
Start With the Contract: The Usual Dispute Steps
Many construction contracts set out a ladder of steps, and a party who skips one may find the next one closed. The standard forms published by AIA Contract Documents are a common example. AIA describes a three-step process under its A201-2017 general conditions:
| Step | Who acts | What happens |
|---|---|---|
| 1. Initial decision | The Initial Decision Maker, typically the architect or another agreed neutral (A201-2017, Section 15.2) | Reviews the claim, interprets the contract documents and issues an initial decision. AIA says this step is required before mediation. |
| 2. Mediation | A neutral mediator | Non-binding. The mediator helps the owner and contractor look for a resolution; no decision is imposed. |
| 3. Binding dispute resolution | An arbitrator or panel, or a court | Arbitration or litigation. AIA notes that the method is usually chosen in the contract before the project begins. |
Source: AIA Contract Documents, “Resolving Construction Contract Disputes: Your 3-Step Resolution Process” (read November 23, 2026). This is AIA’s general description. Your signed contract, including any edits and the edition used, controls.
Subcontracts and supply agreements often have their own steps, and they may not match the prime contract. One of GCAAM’s neutrals has described a Georgia mediation in which the subcontract required mediation before any demand for arbitration: How a $1 Million Construction Dispute Was Resolved by Focusing on a Payment Bond Claim.
Mediation, Arbitration and a Special Master Compared
Georgia rules are used as the example. A contract can add steps or change the order.
| Mediation | Arbitration | Special master | |
|---|---|---|---|
| How it starts | Contract clause, agreement of the parties, or court referral | A written agreement to arbitrate | A judge’s order in a pending lawsuit, on motion or on the court’s own motion |
| Who decides | The parties; the mediator decides nothing | The arbitrator or panel | The master rules or recommends within the order; the judge reviews |
| Georgia authority | Supreme Court ADR Rules; Uniform Mediation Act | Georgia Arbitration Code, O.C.G.A. § 9-9-1 and following | Uniform Superior Court Rule 46 |
| Review of the result | None needed; no agreement unless all sign | Court confirms unless one of five statutory grounds is shown | Motion to reject or modify within 20 days; facts and law decided de novo |
| Who pays the neutral | The parties, per the provider’s fees or their agreement | As the agreement or the award provides | The parties, as the court allocates |
Sources: Georgia Supreme Court ADR Rules, Appendix A, Rule 2; O.C.G.A. §§ 9-9-2, 9-9-3, 9-9-12, 9-9-13 and 9-9-17; Uniform Superior Court Rule 46(A), (G) and (H).
Mediation: A Negotiated Result
Mediation fits anywhere on the ladder. It can be the contract’s required step, a voluntary session before anyone files, or the result of a court referral. In Georgia, any contested matter filed in superior or state court may be referred to mediation, and the order must say that settlement is not required (Uniform Rules for Dispute Resolution Programs, Rule 2).
Three features matter in construction cases:
- Several parties can sit down together. A mediator can meet with an owner, general contractor, subcontractor, supplier and surety in one process, as long as each agrees to come. An arbitrator has authority only over those bound by an arbitration agreement.
- The result can be commercial. A settlement can include payment schedules, repairs, releases of lien or bond claims, and terms for finishing the job. An award or judgment decides the claims put before the arbitrator or court.
- Nothing is decided unless everyone signs. If the session ends without agreement, the parties move to the next contract step. See What Happens If Mediation Fails in Georgia?
Arbitration: A Binding Award Under the Georgia Arbitration Code
Georgia’s Arbitration Code gives construction contracts special mention. For construction contracts, construction warranty contracts and contracts for architectural or engineering design, the Code “shall provide the exclusive means by which agreements to arbitrate disputes arising under such contracts can be enforced” (O.C.G.A. § 9-9-2(b)). The Federal Arbitration Act, 9 U.S.C. § 2, also makes written arbitration clauses in contracts involving commerce enforceable. Which law governs a given project is a question for counsel.
Under the Georgia Code:
- The clause is enforceable. A written agreement to arbitrate an existing or future controversy is enforceable, and a court can order a party to arbitrate (§§ 9-9-3 and 9-9-6(a)).
- Related arbitrations can be joined. Unless the agreement says otherwise, a court may consolidate separate arbitrations that arise from the same transactions and share common issues that could lead to conflicting rulings (§ 9-9-6(e)).
- The arbitrator controls the evidence. Arbitrators can issue subpoenas, and discovery follows procedures the arbitrators set (§ 9-9-9).
- The award is hard to undo. A court confirms an award unless one of five statutory grounds for vacating it is shown (§§ 9-9-12 and 9-9-13). In a 2021 decision, the Georgia Supreme Court called those grounds exclusive and, discussing an earlier construction case, said an erroneous calculation of damages alone does not permit a court to vacate an award (Adventure Motorsports Reinsurance, Ltd. v. Interstate National Dealer Services, Inc., 313 Ga. 19).
Binding or Non-Binding Arbitration? sets out the five grounds and the deadlines, and Arbitration in Georgia: How the Georgia Arbitration Code Works covers the process from demand to judgment.
Special Masters: Help for the Judge in a Filed Case
A special master is not an alternative to a lawsuit. It is a way to manage one. Georgia’s Uniform Superior Court Rule 46 lets a court appoint a master on a party’s motion or on its own. The duties the rule lists include:
- duties the parties consent to;
- pretrial and post-trial matters the court cannot address efficiently or promptly;
- guidance to the court on complex or specialized subjects;
- monitoring compliance with court orders or, in appropriate cases, settlement agreements;
- conducting an accounting; and
- holding trial proceedings and making or recommending findings of fact on non-jury issues where there is an exceptional condition, a need for an accounting, a difficult computation of damages, or “issues for which a special substantive competence would be beneficial” (Rule 46(A)(1)).
What Rule 46 requires
- Notice first. The court must give the parties notice and an opportunity to be heard before appointing a master (Rule 46(B)(1)).
- A written order. It must state the master’s duties, any limits on authority, when the master may speak with the court or one party alone, the record to be kept, the standards for reviewing the master’s work, and how the master is paid (Rule 46(B)(2)).
- The judge stays in charge. A party has 20 days after service to move to reject or modify a master’s order, report or recommendations, unless the court sets a different time. The court decides objections to findings of fact and conclusions of law de novo, unless the parties stipulate to a different standard for fact findings with the court’s consent (Rule 46(G)).
- Cost is weighed. The court should consider the fairness of the likely expense, and it allocates the master’s pay among the parties based on the nature and amount of the controversy, the parties’ means and who is more responsible for the reference (Rule 46(A)(3) and (H)).
A master must have no relationship to the parties, counsel, the case or the court that would disqualify a judge, unless the parties consent with the court’s approval after disclosure (Rule 46(A)(2)). The rule contemplates the parties consenting to a particular person, but the appointment is the court’s. Our planned guide What Is a Special Master, and When Does a Court Appoint One? goes further.
How the Three Fit Together on One Project
These tools are often used in sequence, not as rivals. A contract may require mediation and then arbitration. A case that ends up in court, perhaps because not every party signed an arbitration clause, may be referred to mediation by the judge, and the judge may appoint a special master to manage discovery or an accounting while settlement talks continue. Rule 46 also allows a master to monitor a settlement agreement in appropriate cases.
On timing, see When Is the Best Time to Mediate a Dispute? and Can You Mediate Before a Lawsuit Is Filed? Lien and payment bond rights have their own statutory deadlines. Do not assume that starting mediation or arbitration pauses them; ask a construction attorney licensed in the project’s state.
Construction Neutrals and Fees at GCAAM
GCAAM offers all three services: construction mediation and arbitration and special masters. Barry Selvidge and Wallace Marsh list construction among the practice areas on their GCAAM bios, and Mark Cobb has practiced construction law for more than 25 years and has written and taught on Georgia lien and payment bond law. Barry Selvidge also has more than 35 years in law and business and worked in his father’s commercial construction company early in life. Wallace Marsh’s bio lists mediation only, not arbitration.
Fees are published. Mediation is $500 per party to initiate, plus the neutral’s hourly rate of $100 to $200 per party, with a four-hour minimum per session. Arbitration is $500 per party, per arbitrator, to initiate, plus a $250 administrative fee per party, per day, and the arbitrator’s hourly rate. Claims of $30,000 or less can use the set-fee small claims option. See How Much Does Mediation Cost?, Who Pays for Mediation and Arbitration Fees. Sessions are held in Thomasville, in Atlanta by appointment, or online.
Common Questions on Construction Disputes
Our contract names another organization’s rules or roster. Can we use a GCAAM neutral?
Parties can change their dispute clause by agreement, so it depends on what every party to the clause will sign. Have counsel confirm the change in writing before relying on it, and tell GCAAM which rules the contract calls for.
Can we ask the court for a special master, or hire one ourselves?
Only a court can appoint one, and only in a pending case. Any party may move for an appointment, and Rule 46 allows a master to perform duties the parties consent to. Outside a lawsuit, the comparable private tools are mediation and arbitration.
Can a special master’s ruling be challenged?
Yes, in the appointing court. Rule 46(G) gives a party 20 days after service to move to reject or modify it, unless the court sets a different time, and an order that draws no timely motion has the force of a court order.
Have a Construction Dispute Clause to Act On?
Send us the clause, or the court order, and tell us who the parties are. Use the Schedule a Mediation or Make a Demand for Arbitration form on our Contact page, call 229-226-4818 (South Georgia office) or 404-446-0575 (Atlanta office), or see How to Schedule a Mediation with GCAAM.

Expert review
Mark Cobb is a GCAAM neutral registered with the Georgia Office of Dispute Resolution in general civil mediation, domestic relations mediation and non-binding arbitration, and has practiced construction law for more than 25 years. His review of the rules, fees and procedures described in this guide is in progress. The review date will appear here when it is complete.
Sources
- Uniform Rules, Superior Courts of the State of Georgia (Council of Superior Court Judges, edition dated March 6, 2025), Rule 46, Special Masters (adopted June 4, 2009; amended June 4, 2015): georgiacourts.gov
- Georgia Arbitration Code, O.C.G.A. §§ 9-9-2, 9-9-3, 9-9-6, 9-9-9, 9-9-12, 9-9-13 and 9-9-17, 2025 Code of Georgia (checked November 23, 2026): law.justia.com
- Supreme Court of Georgia, Adventure Motorsports Reinsurance, Ltd. v. Interstate National Dealer Services, Inc., 313 Ga. 19 (2021): gasupreme.us
- Federal Arbitration Act, 9 U.S.C. § 2: law.cornell.edu
- AIA Contract Documents, “Resolving Construction Contract Disputes: Your 3-Step Resolution Process”: learn.aiacontracts.com
- Georgia Supreme Court ADR Rules, Appendix A, Uniform Rules for Dispute Resolution Programs, Rule 2: godr.org