My Contractor Didn’t Finish the Job: Can Mediation Get My Money Back?
ADR Blog › Contractor Didn’t Finish the Job
Short answer
Mediation can get money back from a contractor only if the contractor agrees to a settlement; a mediator cannot order payment. A settlement can also require the work to be finished or repaired. In Georgia, a homeowner must give a licensed contractor written notice of construction defects at least 90 days before suing (O.C.G.A. § 8-2-38). Magistrate court hears claims up to $15,000 ($25,000 from January 1, 2027), and GCAAM offers set-fee mediation for claims of $30,000 or less.
What Mediation Can Get Back, and What It Cannot
A mediator does not award money. In mediation, a neutral helps the owner and the contractor negotiate, and the only outcome is one both sides sign. That limits mediation in one way and widens it in another.
The limit: if the contractor will not come to the table, or will not agree to anything, mediation produces nothing you can enforce. The wider reach: a signed settlement can include terms a court judgment for money usually would not. GCAAM’s Mediation page notes that parties can reach solutions that may not be available in court. In an unfinished-job dispute, settlements are built from terms like these:
- a refund of part of the deposit or of payments made for work not done;
- a dated schedule for the contractor to return and finish, with payments tied to each stage;
- payment toward what a replacement contractor charges to complete or correct the work;
- repair of specific defects by a set date;
- release of a lien the contractor or a subcontractor has filed, and a release of claims in both directions.
Money comes back through mediation only when the contractor agrees to pay it and then pays. A signed agreement is a contract. A planned guide, Is a Mediated Settlement Agreement Binding in Georgia?, explains how one is enforced if a party does not perform.
This guide uses Georgia law as its example because GCAAM is based in Georgia. If the project is in another state, that state’s notice rules and court limits apply instead.
Start With the Contract’s Dispute Clause
Read the written contract before doing anything else. Look for a section headed disputes, claims, mediation or arbitration. It may say that:
- the parties must mediate before either one sues or demands arbitration;
- disputes go to binding arbitration instead of court;
- a named organization’s rules apply, or notice of a claim must be given in writing within a set number of days.
GCAAM’s Construction Arbitration & Mediation page puts it this way: “All good construction contracts have a dispute resolution mechanism, so before you do anything, read the contract. You will have to comply with the requirements in the contract.”
A written arbitration clause can be enforced. Under the Georgia Arbitration Code, a provision in a written contract to arbitrate a later dispute “is enforceable” and gives the courts power to enter judgment on the award (O.C.G.A. § 9-9-3). The Code has exceptions; one is a sales or loan agreement for the purchase or financing of residential real estate unless the clause is initialed by all signatories (O.C.G.A. § 9-9-2(c)(8)), and federal law can apply in place of the state code. Ask a Georgia attorney whether your clause binds you.
If there is no clause, mediation is voluntary and both sides must agree to it. What If the Other Side Won’t Agree to Mediate? covers how to invite a reluctant party.
Georgia’s Right to Repair Act: Notice Before You Sue Over Defects
If the complaint is about defective work on a home, Georgia has a pre-suit notice law, O.C.G.A. § 8-2-35 through § 8-2-43, often called the Right to Repair Act. Its main steps:
| Step | Who | Time allowed |
|---|---|---|
| Written notice of claim, describing the defects in detail | Owner (the “claimant”) | No later than 90 days before filing an action |
| Written response: an offer to settle, or a proposal to inspect | Contractor | Within 30 days after service of the notice |
| Access to the home for inspection, if proposed | Owner | Within 30 days of receiving the proposal |
| Written offer to repair, pay or both, or a written refusal with reasons | Contractor | Within 14 days after the inspection is complete |
| Supplemental offer after a rejection | Contractor | Within 15 days of receiving the rejection |
Source: O.C.G.A. § 8-2-38(a), (b), (e), (f) and (j), checked against the 2025 Georgia Code on November 23, 2026.
Four points about the Act’s reach matter to an owner with an unfinished or badly done job:
- It covers dwellings. A “dwelling” is a single-family house, duplex, or multifamily unit where each residential unit is individually owned (O.C.G.A. § 8-2-36(7)). Commercial projects are outside it.
- It covers “construction defect” claims. The definition reaches design, construction, repair or alteration of a dwelling (O.C.G.A. § 8-2-36(5)). Whether a job that was simply abandoned counts as a defect claim, a plain breach of contract, or both is a legal question for an attorney.
- It applies only to contractors who must be licensed under Georgia’s contractor licensing chapter (O.C.G.A. § 8-2-43(d)).
- The contract can change the process. Where the Act and the contract conflict, “the provisions of the contract shall govern and control” (O.C.G.A. § 8-2-43(c)).
If an owner files without giving the notice, the court or arbitrator must stay the case on request until the owner complies (O.C.G.A. § 8-2-37). An owner who rejects a reasonable offer may also be limited in what can be recovered later (O.C.G.A. § 8-2-38(l)).
Where Mediation Fits in the Notice Period
The Act defines an “action” as a civil lawsuit, judicial action or arbitration proceeding (O.C.G.A. § 8-2-36(1)). Mediation is not on that list. The notice period is built around written offers passing between owner and contractor, and a mediation session is one way to negotiate them face to face. Mediating does not replace the written notice or change its deadlines, so confirm the timing with a Georgia attorney.
Claims of $30,000 or Less: The Small-Claims Option
An unfinished-job dispute is often about a deposit or the cost to complete. For claims seeking $30,000 or less in total damages, GCAAM offers small-claims mediation or arbitration with set fees per party: a $300 initiation fee and a $750 neutral’s fee, for up to five hours of the neutral’s time. A conference room, if needed, is $100 per room, per day, and an online session has no room fee (Small Claims Fees). The Construction page confirms a small-claims version is available for construction disputes.
Both sides must agree to use it, or the contract must call for mediation or arbitration. Each party pays its own share; Who Pays for Mediation, and How Fees Are Split explains the options.
Mediation, Magistrate Court and Arbitration for an Unfinished Job, Compared
Three routes a Georgia owner can take when a contractor walks away. Which are open to you depends on the contract and on whether the contractor will take part.
| Small-claims mediation at GCAAM | Georgia magistrate court | Arbitration | |
|---|---|---|---|
| Size of claim | $30,000 or less in total damages | $15,000 or less; $25,000 or less for actions filed on or after January 1, 2027 | Any, unless the clause sets a limit |
| Does the contractor have to agree? | Yes, unless the contract requires mediation | No | Yes, by a written clause or a later agreement |
| Who decides | The parties. The mediator does not rule. | A magistrate judge | The arbitrator |
| What the result can include | Any terms both sides accept: refund, completion, repair, lien release | A judgment | An award, which a court can enter as a judgment |
| Cost to each party at GCAAM | $300 initiation fee and $750 neutral’s fee, up to five hours | Not a GCAAM service; court fees vary by county | Small-claims arbitration: same set fees for claims of $30,000 or less |
| Pre-suit defect notice for a home | Not an “action” under the Act; the notice still applies before any suit | Notice required 90 days before filing | Notice required 90 days before filing |
Sources: GCAAM Small Claims Fees page; O.C.G.A. § 15-10-2(a)(5) and 2026 House Bill 999; O.C.G.A. §§ 8-2-36(1), 8-2-38(a) and 9-9-3. Checked November 23, 2026.
The Court Alternative: Magistrate Court up to $15,000, or $25,000 From 2027
If the contractor will not negotiate and no arbitration clause applies, court is the alternative. In Georgia, each county’s magistrate court hears civil claims where “the amount demanded or the value of the property claimed does not exceed $15,000.00” (O.C.G.A. § 15-10-2(a)(5)). The limit rises to $25,000.00 for actions filed on or after January 1, 2027 (2026 House Bill 999, sections 3 and 4). Larger claims go to another court.
The two routes differ in kind. A magistrate judge decides the case and can enter a judgment whether or not the contractor cooperates. A mediator decides nothing, and a settlement exists only if both sides sign. A court judgment is for money; a mediated settlement can also require the work to be finished. Filing fees and procedures vary by county, so check with the clerk of the magistrate court.
Time limits apply to lawsuits. Georgia’s limit for actions on simple written contracts is six years after the amount becomes due (O.C.G.A. § 9-3-24); other limits apply to other kinds of claims. Talking, or mediating, does not by itself stop a deadline from running. Ask a Georgia attorney which limit applies to you.
Why a Construction Background in the Mediator Matters
Unfinished-job disputes turn on details: what the scope of work included, what change orders were approved, what was paid against what was built, and what it costs to finish. A mediator who already reads contracts, draw schedules and punch lists can test each side’s numbers without a long explanation.
Mark Cobb has practiced construction law for more than 25 years. His bio lists published work and talks on Georgia lien law, payment bonds and construction contracting, and he is registered with the Georgia Office of Dispute Resolution in general civil mediation. Barry Selvidge’s bio describes early work in his father’s commercial construction company and more than 35 years in law and business. Barry Selvidge and Wallace Marsh list construction among the practice areas on their GCAAM bios; Wallace’s bio lists mediation only, not arbitration. The Construction page says GCAAM’s construction neutrals have represented owners, general contractors, subcontractors and material suppliers.
Where to Go Next
If you are weighing mediation against arbitration or a court-appointed special master for a larger project, read Construction Disputes: Mediation, Arbitration or a Special Master? If the contractor has already agreed to talk, How to Schedule a Mediation with GCAAM shows the steps.
Common Questions
Can I mediate if the contractor has stopped answering?
Not until the contractor agrees to take part or a contract clause or court requires it. A short written invitation that names a neutral and proposes dates is the usual first step; a lawsuit or a demand for arbitration under the contract are the routes that do not depend on consent.
Does the business owner’s side differ from a homeowner’s?
Yes. Georgia’s Right to Repair Act notice applies to dwellings, so a business with an unfinished commercial build-out looks first to the contract’s own notice and dispute clauses. The construction page notes that many AIA contracts let the parties choose mediation and arbitration.
The contractor filed a lien on my property. Can that be part of the mediation?
Yes. The parties can agree that a lien will be released as part of a settlement. Lien deadlines and procedures are set by statute, so get legal advice on them separately.
Do I need a lawyer for this kind of mediation?
Georgia law does not require one for a private mediation. See Do I Need a Lawyer to Go to Mediation?
Ready to Ask the Contractor to Mediate?
Call 229-226-4818 (South Georgia office) or 404-446-0575 (Atlanta office), or email [email protected]. Sessions are held in Thomasville, in Atlanta by appointment, or online.

Expert review
Mark Cobb is a GCAAM neutral registered with the Georgia Office of Dispute Resolution in general civil mediation, domestic relations mediation and non-binding arbitration, and has practiced construction law for more than 25 years. His review of the rules, fees and procedures described in this guide is in progress. The review date will appear here when it is complete.
Sources
- Official Code of Georgia Annotated, O.C.G.A. §§ 8-2-35 through 8-2-43 (resolution of construction defect claims), § 15-10-2 (magistrate court jurisdiction) and § 9-3-24 (written contracts). Official code text current to August 2024, read at archive.org; free public access to the current code: LexisNexis. All three were checked against the 2025 Georgia Code on November 23, 2026: law.justia.com
- 2026 House Bill 999, as passed, sections 3 and 4 (magistrate court civil limit raised to $25,000.00 for actions filed on or after January 1, 2027), Georgia General Assembly: legis.ga.gov; both versions of O.C.G.A. § 15-10-2: law.justia.com
- Georgia Arbitration Code, O.C.G.A. §§ 9-9-2 and 9-9-3 (text hosted by the Georgia Office of Dispute Resolution): godr.org. The sections cited were checked against the 2025 Georgia Code on November 23, 2026: law.justia.com
- Georgia Office of Dispute Resolution, neutral directory (registration categories, checked November 12, 2026): gcr.onegovcloud.com
- GCAAM, Construction Arbitration & Mediation, Small Claims, Small Claims Fees, Mark Cobb and Barry Selvidge pages (checked November 23, 2026); Barry Selvidge and Wallace Marsh bios (practice areas checked November 24, 2026)
Statutes checked November 23, 2026. This guide describes Georgia law in general terms and is not legal advice. Notice rules, deadlines and court limits differ by state and by contract. For advice about your own project, talk to an attorney licensed in Georgia or in the state where the work was done.